Instructions
To prevent processing delays, submit a completed application at least 60 days before the planned installation. Send a check or money order payable to the Department of Inspections, Appeals, & Licensing for the amount owed.  

Submit a single electronic plan with sufficient resolution so no detail is lost when enlarged.

Fee(s)

  • Base fee: The base fee for a construction personnel hoist (CPH) is $500.  
  • Jump Inspection Fee: You must submit a $150 inspection fee with this application for each time you plan to jump (or increase) the number of floors served.

Inspections
A CPH must be inspected prior to first use, at least once each quarter, and prior to the first use after additional floors are added. The Department of Inspections, Appeals, & Licensing must be notified at least seven days before a planned jump inspection.

General Contractor Information

Section 2 of 4 in this document

Jobsite Information

Section 3 of 4 in this document

Elevator Information

Anticipated Removal Date

Jump Information

Cost per jump is $150.

Base fee is $500.

Jump Cost

Total Cost

Upload site plans